Practical risk management for EPC / design-build projects: manage risks effectively - stop the losses
- New Jersey John Wiley & Sons, Inc. 2020
- xix, 299 p.
TABLE OF CONTENTS Foreword xiii
Preface xv
Acknowledgements xix
1 Introduction 1
1.1 The Book’s Focus and Objectives 1
1.2 The Book’s Content and Structure 4
1.3 Generality of Contractual Advice Given 7
1.4 Common Elements for Construction Projects 8
2 Construction Project Implementation Routes 11
2.1 Different Approaches 11
2.2 Traditional Contracting Approach 11
2.2.1 Design Team’s Appointment and Role 11
2.2.2 Employer’s Participation 12
2.2.3 Contractor’s Role and Responsibilities 13
2.2.4 Traditional Approach Advantages 13
2.2.5 Traditional Approach Disadvantages 14
2.3 Design-Build Approach 14
2.4 EPC Approach 16
2.4.1 EPC Project Suitability 16
2.4.2 Contractor’s Obligations 17
2.4.3 Employer’s Participation 17
2.4.4 Standard EPC Contracts Available 18
2.4.5 General Notes of Interest 20
2.5 EPCM Approach 21
2.6 Employers Prefer Lump-Sum Contracts 23
2.7 Fixed-Price Lump-Sum Contracts 25
2.8 Selecting the EPC Contractor 26
3 EPC Project Risk Management Overview 29
3.1 Project Risk Management – Definition 29
3.2 Construction Project Hazards Abound 29
3.3 Importance of Project Risk Management 31
3.4 Corporate Risks Versus Project Risks 32
3.5 Greater Risks for EPC Contractors 33
3.6 Principal Disaster Areas on EPC Projects 34
3.7 Maintaining the Project Schedule 36
3.8 Departmental Interface Issues 36
3.8.1 Rework 37
3.8.2 Delayed Technical Bid Evaluations 38
3.8.3 Late Mobilisation of Procurement Team 38
3.8.4 Red-Line Drawings Left Too Late 39
3.9 Forging an Integrated Implementation Team 39
3.10 Allocating Responsibility for Handling Risks 40
4 EPC Project Pre-Implementation Problems 43
4.1 Bidding Process Pitfalls 43
4.2 Failure to Embrace Lessons Learnt 44
4.3 Failure to Understand Contract Terms 45
4.4 Qualifications, Deviations and Exceptions List 46
6.14.5 Reducing Quality Control Risks on the Site 166
6.14.6 Reducing Vendor Quality Control Risks 167
6.15 The HSE Manager 167
6.15.1 Importance of HSE Inputs from Everybody 167
6.15.2 Primary Responsibilities 168
6.15.3 Safety Provisions and Training 168
6.15.4 Enforcing HSE Rules to Prevent Accidents 169
6.15.5 Motivating On-Site HSE Officers 170
6.15.6 Off-Site HSE Incidents 170
6.15.7 Safety Moment Chats 171
6.16 The Camp Boss 171
6.16.1 Primary Responsibilities 171
6.16.2 Major Risks 172
6.17 The Project Information Manager 173
6.17.1 Importance of Information Management 173
6.17.2 Information Overview 173
6.17.3 Electronic Document Management Systems 174
6.17.4 PIM Role and Primary Responsibilities 176
6.17.5 Major Risks for the PIM 177
6.17.6 Dedicated Data Inputters 177
6.17.7 Information Management Support Personnel 178
6.18 The Document Control Manager 179
6.18.1 Standardised Document Management System 179
6.18.2 Controlling Communications 180
6.18.3 Vetting Documents Before Issuing 180
6.18.4 Restricting Email Usage 181
6.18.5 Benefits of a Standard Documents Library 181
6.19 The Information Technology Manager 182
6.19.1 IT System Security 182
6.19.2 Backing Up Work from Personal Computers 182
6.19.3 Ensuring Integrity of Computerised Data 182
6.19.4 Reducing Contractor’s Software Costs 183
6.20 The Interface Manager 184
6.20.1 Primary Function and Responsibilities 184
6.20.2 Interface Management Plan 184
6.20.3 External and Internal Interfaces Explained 185
6.20.4 Identifying/Locating Interfaces 186
6.20.5 Interface Slip-Ups 187
6.20.6 Closing Interface Activities is Hard Work 188
6.21 The Contract Administration Team 189
6.21.1 Determining the Compilation of the Team 189
6.21.2 The Project Contract Manager 190
6.21.3 The Contract Administration Manager 190
6.21.4 The Subcontracts Manager 191
6.21.5 Compiling the Contract Summary 192
6.21.6 Identifying Risk Exposure 192
6.21.7 Importance of Keeping Records 193
6.21.8 Risk of Collusion in Measurement/Costing Team 195
6.21.9 Facilitation Role of the Contract Administration Team 195
6.21.10 Illusory Claims 196
6.22 The Human Resources Manager 196
6.22.1 Primary Responsibilities 196
6.22.2 Becoming the Employer of Choice 197
6.22.3 Recruitment Issues 198
6.22.4 Emergency Replacement for Key Personnel 199
6.23 The Administration Department 200
6.23.1 Primary Responsibilities 200
6.23.2 Providing Back-Up Support to Site Quickly 200
6.24 The Financial Management Team 201
6.24.1 Primary Responsibilities of Finance Manager 201
6.24.2 The Budget Controller 202
6.24.3 Controlling Purchases 203
6.24.4 Keeping Track of Expenditure 204
6.25 The Compliance Team 204
6.26 The Legal Department 206
6.26.1 Utilising External Legal Team 206
6.26.2 Utilising Dispute Adjudication Boards 207
7 Reducing Joint-Venture/Consortium Risks 209
7.1 Joint Venture Versus Consortium 209
7.2 JV Considerations 209
7.3 Setting Up a JV Steering Committee 210
7.4 Objectives of JV Steering Committee 211
7.5 JV Members are Partners 212
8 Claims Management Risks and Problems 215
8.1 Relying on Claims to Achieve Profitability 215
8.2 Factors Legislating Against a Claim’s Success 216
8.3 Key Ingredients for Worthwhile Claims 217
8.4 Proving Excusable Delay 217
8.5 Key Components of Successful Claims 218
9 Identifying Hazards and Managing the Risks 219
9.1 Introduction 219
9.2 Potential Hazards for Construction Projects 220
9.3 Responsibility for Project Risk Assessment 222
9.4 Identifying and Managing Project Risks 224
9.5 Project Main Risks Register 227
9.6 Risk Assessment Team Inputs 228
9.7 Relative Risk Factor Assessment 229
9.8 Risks Arising from Safety Studies 230
9.9 Dealing with Safety Risks to On-Site Personnel 232
9.10 Dealing with Health Matters for On-Site Personnel 236
9.11 Dealing with Risks to the Environment 237
List of Figures:
Figure 6.1 Interfaces for EPC Project’s Departments and Teams 114
Attachments:
Attachment A Matrix of Project Risk Areas and Corresponding Risk Management Solutions 239
Attachment B Matrix of Prime Risk Considerations, Impacts & Consequences 243
Attachment C Example Project Main Risks Register 245
Attachment E Task Hazard Assessment Worksheet 251
Appendices:
Appendix A Abbreviations and Acronyms 253
Appendix B Glossary 255
Appendix C EPC Project Management Team Organisation Structure 269
Appendix D EPC Project Departmental Organisation Structure 271
About the Author 275
Index 277
DESCRIPTION Many of the books on construction risk management concentrate on theoretical approaches to the accurate assessment of the overall risks of taking on a new project. Less attention is paid to the typical risks to which the operational level of a project is exposed and how operational managers should approach those risks during project implementation. This book identifies precisely where the major EPC/Design-Build risks occur within an operational framework and shows how best to deal with those risks. The book attempts to offer practical advice, approaches and tools for dealing with risks to which the various operational departments are exposed.
9781119596172
Risk management Project management Engineering design Construction industry--Management